From the corner of Dakota Boulevard and 2nd Street, the old Foothills North Trail climbs straight up the hill, the way many older trails do. This summer a contractor began replacing it with a route that rises at 4 to 8 percent, is surfaced in crushed gravel, and is wide and smooth enough for a three-wheeled mountain bike. The City of Boulder's Open Space and Mountain Parks department says one goal is "a more consistent trail quality and experience" with the trails it has already rebuilt in western Boulder Valley Ranch.
That goal is the real story behind the construction fencing. OSMP is rebuilding the trail behind Dakota Ridge to the same standard as the ranch trails on the other side of US 36. By the end of 2026, if the schedules hold, the hillside behind 2nd Street becomes the western end of a single north Boulder trail system built to one specification.
A Quarter Mile Along 2nd Street Has Been Open Since July
The new trail is opening in pieces. Timberline Trailcraft, OSMP's contractor, is building from south to north, and each finished section opens when it's ready. The first one, roughly a quarter mile running parallel to 2nd Street, opened at the end of July. By then the city reported that a large part of the reroute was built, from Dakota Boulevard and 2nd Street up to the plateau west of the neighborhood.
The whole reroute covers about 1.3 miles. About 0.85 mile of old trail will be closed and replanted with native vegetation. So the corridor ends up with more trail on a gentler line and less ground torn up. Construction is scheduled from mid-June through December 2026, weather permitting.
The Boulder Mountainbike Alliance, which toured the work with OSMP and Timberline, ended its July update with this request:
"Until each section officially opens, please respect construction closures and give the crews room to work. Fresh dirt is exciting, but it rides much better after the contractor says it is ready."
What Changes, From the Highway Down to 2nd Street
The BMA's breakdown of the planned work reads like a walk along the corridor, starting at the Foothills Trailhead and heading south toward the neighborhood.
- The Highway 36 underpass stays as it is. All the work happens west of the highway.
- The trail leaves the rocky ravine. One section moves up onto the hillside to deal with drainage and erosion.
- Foothills meets North Sky at bridge level. The junction with the North Sky Trail lines up with the bridge, so riders no longer drop down and climb back up.
- The route under the bridge goes away. The trail no longer passes under the bridge or climbs the steep hill to the cloverleaf entrance.
- The steep pitches west of 2nd Street get a new alignment. These are the sections closest to Dakota Ridge homes.
The BMA notes that the final alignment was still being designed and could shift to fit site conditions. According to the city, the new line also improves connections to the Hogback Ridge Trail and the neighborhood access trails along 2nd Street.
Two ecological factors shaped where the trail goes. The new alignment avoids habitat for Bell's twinpod, a rare plant that grows in only a few places in Boulder and Larimer counties. It also moves the trail out of low-lying wetland that OSMP describes as high-value habitat for plants and wildlife. The gravel surface and frequent drainage features are meant to cut down on the seasonal mud the old line was known for. The BMA expects the crushed aggregate to keep the trail open more often in wet weather.
Built for a Three-Wheeled Bike
Adaptive design is the clearest link between this project and the ranch trails. The city says the Foothills North reroute is being built for adaptive mountain bikes, which it describes as three-wheeled bikes used by people with disabilities. One of its project photos shows an adaptive rider testing a new section.
OSMP set this precedent in November 2024. It opened a half-mile reroute of the Eagle Trail south of the Boulder Valley Ranch Trailhead, open to hikers, bikes and horses and designed for hand-pedaled adaptive cycles. When the Boulder Reporting Lab covered that opening, OSMP spokesperson Phil Yates explained that modest design changes to grade, cross slope and width can make a trail welcome more visitors. The Foothills North work applies the same three changes to the hill behind Dakota Ridge.
The rocks are there for other riders too. The hillside is full of stone, and Timberline is using it to build optional features beside the trail, along with turns shaped for bikes. The BMA sums up the result as "a smoother and more accessible trail, with a few opportunities to play along the way."
OSMP runs adaptive bike rides on its lands for people with disabilities. Routes range from 2 to 20 miles, from easy to difficult terrain, and the bikes' power assist can make a ride possible for someone without a strong upper body. OSMP also offers rides for non-disabled participants, including trail designers and builders, so they can learn what slope, turning radius and width these bikes need.
The Same Standard Across Highway 36
From the Foothills Trailhead, a short trip up North Broadway puts you on the Eagle, Degge and other Boulder Valley Ranch trails. OSMP has been rebuilding those trails since 2024 under the same 2016 plan that calls for the Foothills North work: the North Trail Study Area Plan, which went through extensive community input and was approved by the Open Space Board of Trustees and City Council. The plan calls for fewer trails of higher quality, conversion of some trails to allow bikes, and closures to protect habitat.
Here is where each piece stood in the most recent official updates:
| Trail | What's being done | Status in latest update | Bikes |
|---|---|---|---|
| Foothills North | About 1.3-mile reroute behind Dakota Ridge | Southern quarter mile open since late July 2026; full project due by December | Yes, adaptive-ready |
| Eagle | Two reroute phases at Boulder Valley Ranch | Half mile opened November 2024; mesa-top phase finished April 2025 | Yes, adaptive-ready |
| Shale | New 2/3-mile trail from the trailhead to the mesa top | Construction began April 2025, expected to last into summer | No, hikers and horses only |
| Degge | Reroute | Open to hikers as of January 2026 | Expected by end of 2026 |
| Hidden Valley | Reroute | Construction set for summer 2026 | Expected by end of 2026 |
| Mesa Reservoir | Closure for habitat | Planned closure | Closing |
According to OSMP's January 2026 update, the Hidden Valley reroute is being built by OSMP trail crews, volunteers and the Boulder Mountainbike Alliance. When it's finished, expected by the end of 2026, Degge and Hidden Valley will both open to multiuse access. The city's 2026 projects list gives Hidden Valley a May through November work window and Foothills North a July through December window. Both windows close before the end of the year. I couldn't find any official notice that Hidden Valley has opened to bikes yet, so for now treat that opening as scheduled, not done.
Shale Trail is the counterweight. OSMP designed it as a hiking and equestrian route to the mesa top so the area keeps a path without bikes as bike access grows elsewhere.
Between Now and December
I haven't seen an official update since July that says which other Foothills North segments have opened or confirms that the old segments are already closed for restoration. Here is what's confirmed as of early October:
- The quarter-mile section along 2nd Street is open. Everything north of it opens section by section as Timberline finishes.
- Some segments may close temporarily during construction. Once the new trail is in, the old sections will close for good and be replanted.
- OSMP posts closures on its current trail closures page, which is the most reliable place to check a segment before you head out.
- The project page has the reroute map, with the old alignment in green and the new one in yellow.
- The Western Boulder Valley Ranch project page is where OSMP has posted status updates for Degge and Hidden Valley.
If the December finish holds, the climb from Dakota Boulevard and 2nd Street will run on a gravel, adaptive-ready line that meets North Sky at bridge level and continues toward Boulder Valley Ranch trails rebuilt to the same specification.
A rebuilt trail changes how a house relates to the hillside behind it, from which gate gets used most to how the back of a lot reads from the path. If you live near 2nd Street and are thinking about how your home presents now that the trail behind it is changing, Debby Caplin can walk the property with a designer's eye. Get your instant home valuation + design consult.